7th July Isiolo Circumstances have prevented me from posting a report until to-day.
The home at Wamba will enter the home stretch for phase 1 next week with the beginning of second fixing. The roof is already complete.We are optimistic that another charity will dig a 70 meter borehole for us if they can confirm water on the site - Government supply has been problematic.
On Wed we will travel to Rendille with well digging team staying till Fri and leaving them to prepare the first borehole. Two Afridev have been ordered for the wells. Sat we hope to rest and Sunday we are entertaining visitors from the Salvation Army including a leader and his wife from USA.